Westband Construction (Change Orders) Construction Articlee

In: Other Topics

Submitted By nunna2
Words 2049
Pages 9
How to prepare a claim in construction projects

WESTBAND CONSTRUCTION LTD.
9910 39 Avenue
P.O. Box 2408 Edmonton, Alberta T5J 2R4

October 27 - 2011

City of Edmonton Drainage Branch

Dear Madam / Sir,

Request for Change Order:

Regarding to our meeting dated July 30, 1993; WestBan Construction Limited needs City’s approval for extra time and cost to precede with additional scope of the construction work (changing slope in North and East banks, adding required shoring for stabilizing the soil, leaving shoring in the ground, pouring tank concrete walls instead of shotcrete), according to the option B for both North and East Slopes (Attachment F2), the chosen schemes for slope remedies are attached in this document.

WestBan, due to the delays of City of Edmonton and UMA in providing requested services to this company, believed that the justifications in cost and schedule are necessary to complete the project within satisfactory quality.

WestBan is proposing extra CAD$72,500 and additional 28 days to the original project duration according to general conditions to the contract clauses 410.1, 404.3 and 404.4. It is noteworthy that the total amount of money requested is additional to the insurance of North and South slopes which stipulated in Attachment G Section 1.2 (Course of Construction Insurance). The detailed cost breakdown and the revised schedules are attached for references.

The revised milestone dates are as followed:
Completion of Storage Tank: 17-Sept-1993
Completion of Mech./Piping: 08-Oct-1993
Completion of Electrical/Control: 15-Oct-1993
Substation Completion: 12-Nov-1993

We appreciated your considerations regarding this change order.

Sincerely Yours,
Project Manager, WestBan Construction Limited.

The change order is requested…...

Similar Documents

Construction

...contract is: | (1point) | | | performed | | | | | implied-in-fact | | | | | executory | | | | | quasi-executed | | | | | executed | | | | | | Score: 1 | | | | | | | 23) | Which of the following is NOT needed in order to have a valid contract? | (1point) | | | a signed written document | | | | | contractual capacity | | | | | a legal object | | | | | an agreement | | | | | consideration | | | | | | Score: 0 | | | | | | | 24) | When the other party commits an anticipatory breach, the nonbreaching party: | (1point) | | | is immediately discharged from her own duties | | | | | is usually able to seek specific performance | | | | | must wait until the performance was due before suing | | | | | is not able to seek damages because she received advance notice of the breach | | | | | | Score: 0 | | | | | | | 25) | George, an employee, breaches a fixed-term employment contract by quitting before the end of the term. What can his employer, MNO Inc., recover as damages? | (1point) | | | nothing, because courts do not order anyone to perform a job against his or her will | | | | | only amounts paid to the employee for which the employee has not yet done the work | | | | | all amounts already paid to the employee under the contract | | | | | the costs of hiring a......

Words: 1613 - Pages: 7

Construction

...Gotzman Faculty of Engineering and Computer Science Concordia University 1515 St. Catherine west Montreal Quebec H3G 2W1 Subject line: Course ENCS 6721, Sec. UU, Assignment #1 Dear Ms. Gotzman I am Mahmoud Elhuni a civil engineer. I got my bachelor degree at Civil Engineering from Tripoli University. I have six year experience in civil work scope in three deferent construction firms. In addition, I have good skills at several engineering program such as AutoCAD, SAB, Project Plan software and Microsoft Office. Moreover, I've invented a device to settle the level of sewage pipes during installation, and I am working to register my invention. My mother language is Arabic, and I speak English as second language. Currently, I am a graduate student in Master degree program at Concordia University, and I am studying construction management in building engineering department. I am interesting at construction management major because I would like to improve my knowledge in project management planning and controlling. Also, I am willing to study construction processing and controlling project cost by preparing an accurate project cost estimate. My research is about how to estimate the cost of a project by establish an energy unit to estimate the energy that expended in that project. In reality, building the same project in two different cities has different costs. Therefore, instead of estimating the project cost twice, I will estimate the......

Words: 363 - Pages: 2

Construction

...CONSTRUCTION In the fields of architecture and civil engineering, construction is a process that consists of the building or assembling of infrastructure. Far from being a single activity, large scale construction is a feat of human multitasking. Normally, the job is managed by a project manager, and supervised by a construction manager, design engineer, construction engineer or project architect. For the successful execution of a project, effective planning is essential. Involved with the design and execution of the infrastructure in question must consider the environmental impact of the job, the successful scheduling, budgeting, construction site safety, availability ofbuilding materials, logistics, inconvenience to the public caused by construction delays and bidding, etc. Types of construction projects In general, there are four types of construction: 1. Residential Building construction 2. Industrial construction 3. Commercial Building construction 4. Heavy Civil construction Each type of construction project requires a unique team to plan, design, construct and maintain the project. Building construction Building construction is the process of adding structure to real property. The vast majority of building construction jobs are small renovations, such as addition of a room, or renovation of a bathroom. Often, the owner of the property acts as laborer, paymaster, and design team for the entire project. However, all building construction projects include some...

Words: 3036 - Pages: 13

Construction

...MAPPING THE CONSTRUCTION ENGINEERING AND MANAGEMENT DISCIPLINE By Mohamed A. Aboulezz A Thesis Submitted to the faculty of the WORCESTER POLYTECHNIC INSTITUTE In partial fulfillment of the requirement for the Degree of Master of Science in Construction Project Management February 2003 Approved Prof. Roberto Pietroforte, Thesis Advisor Prof. Fredrick L. Hart, Head of Department Abstract The objective of the study was to map the structure of the construction engineering and management (CEM) discipline and its contents, trace its evolution, and to identify the most prevailing research areas in the discipline. The study entailed a review of the literature in construction engineering and management as well as two of the leading academic journals in the discipline, particularly a bibliometric study of the contents of the ASCE Journal of Management in Engineering (JME), as a case study of the CEM refereed journals. The JME’s contents were investigated from its onset in 1985 until 2002. The results of the analysis show that 70% of the published papers focused on four main subjects: management and organization of the firm, project management, industry structure and environment, and management of personnel. Considerable changes occurred within the subjects with the emergence of new topics and the decline of others over the eighteen years of publication. The study also analyzed the use of keywords, research methods, and identified authors, and the concentration......

Words: 24458 - Pages: 98

Construction

...For construction projects, quality control means making sure things are done according to the plans, specifications, and permit requirements. Quality is defined as 'fitness to purpose', in regards to how quality is significant for Bull’s Construction. It means providing a building that has an appropriate quality for the purpose for which it is intended. Moreover, a different way of looking at this concept is that the price of the building could potentially reflect the expectations of quality. A cheaper building probably uses inferior materials and is likely to be less attractive and less durable. Quality control in construction typically involves insuring compliance with minimum standards of material and workmanship in order to insure the performance of the facility according to the design. These minimum standards are contained in the specifications described in the previous section. For the purpose of insuring compliance, random samples and statistical methods are commonly used as the basis for accepting or rejecting work completed and batches of materials. Rejection of a batch is based on non-conformance or violation of the relevant design specifications. Procedures for this quality control practice are described in the following sections. One of the elements that our company will be utilizing to assure a quality measurement process for our projects is an inspector. An inspector tries to ensure that the job is done right the first time and that no major accidents......

Words: 1054 - Pages: 5

Construction

...Lotus Riverside Complex failed due to many construction errors such as faulty foundation and improper assessment of environment before construction. The workers while excavating the dirt for the garage dumped the dirt on the opposite side of the building. When it rained the excavation started to fill with water and the pressure from the dirt changed the water table of the ground and created three thousand tons of force along with uneven lateral pressure and thus the pilings in the ground to support the building gave way and snapped off sending this thirteen story high building tumbling right over. The building was surrounded by other buildings but was far enough not to affect any of the other surrounding buildings. Engineers who came to the scene of the fallen building said that if the building would have come in contact with other buildings it could have created a domino effect and wiped out a total of nineteen buildings in a matter of minutes. This building disaster could have easily been avoided if the head engineers would have took the time out to calculate the water table around the complex and properly calculated how many pilings would accurately be needed in order to properly secure this building. It was also discovered that the rebar that was supposed to be used was not used at all because they construction supervisors were behind schedule so they decided to skip that step and go directly into the excavating process. Construction errors and ignoring proper......

Words: 991 - Pages: 4

Construction Materials

...more adaptive companies are entering the market with new concepts that are more responsive for the consumer’s changing preferences (Esquivias et. al., 2010). The construction industry is also highly connected with innovations in terms of achieving efficiency and cost effectiveness (NRC, 2013). This report will be based on the innovative concrete products, particularly analyzing Ultra-High Performance Concrete. Furthermore, other existing modern trends and issues of concrete industry are also will be examined in brief. Concrete industry According to the World Business Council for Sustainable Development (2012), concrete plays a significant role in the modern world. Being used for construction of the majority hospitals, residential and commercial buildings, schools, bridges, runways, roads it actually shapes the built environment around us (WBCSD, 2012). Moreover, with global annual concrete production of almost 3 tons per every human in the world, it is become the most used man made material in the world. Additionally, comparing to the other building materials such as steel, plastic, wood and aluminium the amount of concrete used globally is twice as much than all of them together (WBCSD, 2012). The modern construction industry trends are closely linked with innovations of new materials, improvement of construction techniques and research is done continuously to improve economy and increase durability (Hooda et al, 2013). The manufacturers of concrete are also compelled......

Words: 1217 - Pages: 5

Construction

...It introduces what is meant by principled negotiation in dealing with construction conflicts. It describes the theoretical background on how to have a successful negotiation for both contracting parties, namely employer and contractor. During the negotiation process, several options for mutual gain or “win-win” situation will be looked into before applying objective criteria to reach the settlement. Finally, we will discuss few case studies that related to negotiation in construction industry. Learning Objectives By the end of Unit 1, you should be able to: Identify questions check list for negotiation prior implementation; Explain the application of principled negotiation into construction industry; Apply appropriate techniques of negotiation in reaching the settlement in construction industry; 1.1 Question check list for negotiation a typical project consists of six stages, which are: 1. Conceptual stage 2. Budgeting stage 3. Design stage 4. Tendering stage 5. Construction stage 6. Post-construction stage 1.1 Question check list for negotiation the adversarial relationship: • • • • Between employer and contractor Between architect and quantity surveyor Between quantity surveyor and contractor Among architect, employer and contractor 1.1 Question check list for negotiation Some guidelines are proposed as a reference to determine the situation that required negotiation in the construction industry, for instance: • There is still room for discussion on the......

Words: 1528 - Pages: 7

Construction

...can be readily accessed by geographical location of the site. Past construction records for both the site and for adjacent properties are useful for site investigation. Several government departments posses valuable information for the planning and execution of the site investigation. They are the Civil Engineering Department, Building Ordinance Office, Highways Department, Water Supplies Department, Drainage Services Department, and Architectural Services Department. Non-government agencies such as Mass Trainsit Railway Corporation and other utility companies can also provide valuable information on past construction records. Services records are also an essential part of the desk study, necessary to locate hidden services such as electricity cables, sewers and telephone wires. This in formation is usually provided free of charge by the relevant service provider. A suggested list of sources is: Water Supplies Department, Drainage Services Department, Mass Trainsit Railway Corporation, The Hong Kong Electric Company, Hong Kong & China Gas Company, all telecom company etc… Aerial photographs can be used in the preparation and revision of maps and plans, and they can assist in the identification and general assessment of natural and man-made features, including geology, geomorphology, hydrology and vegetation on or in relation to a site. They are particularly useful in the assessment of site history (i.e. changes in form, materials and land use) and can provide valuable......

Words: 5262 - Pages: 22

Construction

...Current Material Selection Overview A survey which conducted to investigate the criteria of the selection of construction material from the perspectives of architect, builder, engineer, product manufactures,etc. The participants of the survey included the following categories of professionals: Architects: 48%; General Contractors and Builders: 4%; Engineers: 12% including engineering consultancy firms; and Others-36% including Materials Specifiers and Quantity Surveyors, Product Manufacturing consultancy, Green building Proponents, Program Designers, Green Building/net-zero Consultants and researchers . The distribution of the survey tool across the USA, UK, and China was based on their geographic variations. The result of the analysis showed that the majority of users rarely consider the relevant factors when selecting building materials or products. Over half of respondents showed that they selected material only based on the previous experiences or individual preferences. Besides, the survey assessed the views of targeted experts of various disciplines and geographical settings, to the likelihood of the impacts of other potential factors involved in making strategic decisions during material-selection. 96% identified “Environmental and Health factors or Buildings variables” as the most desirable content information for enabling effective and sustainable decisions in selecting appropriate materials. There was a tie between two categories of factors as 84% of the sample......

Words: 352 - Pages: 2

British Construction

...15 British Construction Industry 15 British Construction Industry Executive Summary The construction industry of UK has dramatically changed in past 15 years. The main catalyst of this change is the element of partnering, which has taken place of traditional adversarial approach. This concept though is yet new in this particular industry but has been suggested as the critical solution to the downturn of the economic conditions as well as the spiraling issues related to the contracts which had dogged UK construction industry in early 1990s. Latham was the first person who claimed that the partnering might be the only remedy to the fragmented, ineffective and the disputes which are saturating the construction industry which can be replaced with proper procurement, effective communication among different stakeholders, teamwork and fairness. These ideas were endorsed by Egan and proposed set of the recommendations and as the result, the outcome would be much improved relations among the three major stakeholders within the supply chain which are the main contractor, client and sub-contractor. Majority of the highly profiled clients have already embraced this new concept like education, local authorities, NHS, water companies in UK. Companies like Severn Trent Water and Yorkshire also used partnering as well as framework agreements, which are inspired by the reports of Latham and Egan. Even though after the 12 years of the report of Latham and Egan, still general......

Words: 2692 - Pages: 11

Construction Law

...permits Page 113 One purpose for requiring the issuance of building permits authorizing construction is to ensure that the issuing authority may ensure that the issuing authority may enforce the FBC and the Fire prevention code and thus provide for the safe construction, erection, alteration, repair and demolition of the building. Certain property such as schools federal, and state government faciliteies are not subject to permitting from local authorities State construction falls under the state uniform building code for public educational facilities The contractor will not be required to obtain a local building permit for the construction of the school on school property. However there may be local building permit requirements for utilities outside the school. There is a statutory formal building permit application. The law authorizes the building permit applications to be submitted in electronic form. The building department that accepts service permits in electronic form must provide access to the permit application through internet access in searchable way. A permit may not be issued for any building construction, erection, alteration modification, repair or addition unless the applicant for such permit complies with the requirements for the plan review status within the for the building code However the code shall set standards and criteria to authorize preliminary construction before completion of all building plans review, including but not limited to......

Words: 9315 - Pages: 38

Construction

...Chet Lempitsky Mrs. Figs English 3 10 February 2013 Steroids In many parts of the world today, sports competitions are the vehicle for the fierce quest to win, to be “the best.” Athletes will do anything to win whether that be cheating in golf or taking steroids in order to excel in baseball. It is said that over three million athletes and bodybuilders have used illegal steroids in this country alone (Solberg 92). If many people already use steroids why not make them legal and let people take them at their own risk? Or perhaps do you think steroids should stay illegal because they have harmful side effects and promote an unfair advantage in sports? With the growing concern over steroid use in our country, we must look at what is really best for the future of our athletes and the spirit of competition. Steroids are extra hormones that are either taken orally or injected into the body. Theses hormones set off a reaction that sends an individual’s testosterone level soaring, which in turn allows that person to increase muscle size and strength. But with this new-found strength comes some harmful side effects. Steroids can cause heart attacks or liver cancer, not to mention all the newly acquired acne that often develops. These are only a few of the hundreds of unhealthy things that can happen to you when you are on steroid (Harris129). Many people, medical experts and athletes alike, feel steroids should be legalized. They feel that the use of steroids a few times and in......

Words: 1380 - Pages: 6

Construction

..."we see that construction has two choices: ignore all this in the belief that construction is so unique that there are no lessons to be learned; or seek improvement through re-engineering construction, learning as much as possible from those who have done it elsewhere" egan report. Task force visit to the site. (Rethinking construction) The problems wityh the industry: (Rethinking construction) Nevertheless, the industry recognises that it needs to modernise in order to tackle the severe problems facing it, not least that: 4. it has a low and unreliable rate of profitability. Margins are characteristically very low. The view of the Task Force is that these are too low for the industry to sustain healthy development and we wish to see those companies who serve their clients well making much better returns; l it invests little in research and development and in capital. In-house R & D has fallen by 80% since 1981 and capital investment is a third of what it was twenty years ago. This lack of investment is damaging the industry's ability to keep abreast of innovation in processes and technology; l there is a crisis in training. The proportion of trainees in the workforce appears to have declined by half since the 1970s and there is increasing concern about skill shortages in the industry. Too few people are being trained to replace the ageing skilled workforce, and too few are acquiring the technical and managerial skills required to get full value......

Words: 373 - Pages: 2

Construction

...San Joaquin Valley Online Construction/110 D1 Michael McGuire 05-27-10 Written Assignment 2 Chapter 15 Review Questions 1. How does the type of contract influence the format of the payment request? The contract self dictates payment terms for instance; payment on a lump sum contract allows for payment based upon quantities installed. 4. What is retention? What is it used for? Retention is when you hold back a portion of the monthly pay request with respect to the subcontractor. It is used as a cash tool; this helps bring the subcontractors focus on completing the project. 7. What is interim lien releases used for? Interim lien releases should be collected and filed just in case a problem occurs. Chapter 17 Review Questions 3. Why is project-specific quality control plans needed? Why are generic quality control plan’s unacceptable? Quality control plans and project specific quality control plans are needed to identify quality control systems for each major work package. Generic quality control plans are not accepted because they do not discuss enough detail of the work or specific materials. 4. What are mockups and why are they needed? Mockups are used to establish workmanship standards and they are sometimes used for testing such as climate testing. Written Assignment 3 Chapter 19 Review Questions 4. What is the difference between owners initiated change order proposal and a contractor initiated change order proposal? An owner......

Words: 540 - Pages: 3